Data centre developer Applied Digital has asked tenants including Oracle and Meta for billions of dollars in guarantees before signing leases, Bloomberg reported, according to TNW.[1] The developer is also asking chipmakers Nvidia and AMD for guarantees, a person familiar with the matter said; TNW reported that the guarantees are set case by case and usually cover the cost of grid links.[1]

Utilities used to fund grid upgrades and recover the cost through rates, but now they want the biggest users to carry that cost if a project collapses, TNW noted.[1] Credit ratings now decide who gets space, TNW reported.[1] The pressure is rising after the midterms, where Democrats who campaigned on power bills won key races, TNW wrote.[1]

"Applied Digital prefers to do business with investment-grade tenants, with a preferred mix of 70% investment-grade to 30% non investment-grade," chief executive Wes Cummins said in a statement to Bloomberg.[1] The company has capped how much it leases to junk-rated neoclouds such as CoreWeave, which told Bloomberg its partnership with Applied Digital is strong, TNW reported.[1] "With most new sites, you have to build the power and transmission lines yourself," Applied Digital president Jason Zhang said, according to AI Weekly.[2]

Oracle has already felt this pressure, TNW reported, noting that Wisconsin regulators require large customers rated below A- to post collateral.[1] Oracle said its Lighthouse campus could need more than $7bn, and it sued the regulator in June before dropping the case in August.[1] In Indiana, Nipsco's parent NiSource set up a separate unit, GenCo, so Amazon, Google and Microsoft pay for the power plants that serve them, TNW reported; according to Bloomberg, Nipsco has signed 5 gigawatts of GenCo deals.[1] Barclays estimates hyperscalers will issue $300bn to $320bn of debt this year, TNW reported.[1]

Meta had no comment and Oracle declined to comment, TNW reported.[1] TNW reported that the guarantees are set case by case.[1]