National Grid agreed to buy 29.5 hectares (73 acres) at Dorman Point on Teesside for what could become Britain's biggest electricity substation, able to supply power to a vast neighbouring datacentre, Sky News first reported, according to the Guardian.[1] The land belongs to Teesworks, a local private-public partnership that the UK government was reported last year to have picked as the site of a new AI datacentre.[1] Ben Houchen, the mayor of the Tees Valley combined authority, told Sky News that getting enough power to a site quickly is the biggest problem for datacentre builders, and that up to 3.2GW of capacity there means the region can finally compete for those projects.[1] The land deal brings that power supply a step closer for the planned Teesside datacentre.[1]
National Grid to buy Teesside land for what could be Britain's biggest substation
The land belongs to Teesworks, which the UK government was reported last year to have picked as the site of a new AI datacentre.
0 primary · 1 independent · 0 commentary · 0 vendorUpdate of the earlier story.
Sources
- National Grid to site biggest substation in UK near planned Teesside datacentre the Guardian Independent