Anthropic is in talks with U.K. neocloud Nscale for a second multibillion-dollar deal to lease computing capacity at a site in the U.S., a person familiar with the matter told CNBC.[1] The agreement would cover a second 460-megawatt data center at the same West Virginia site as the first deal, the person said, and could be worth around $45 billion, the person said.[1]
The Monarch campus, enabled by West Virginia legislation allowing data centers to build microgrids, will run on natural gas, raising environmental concerns from groups including the Sierra Club's West Virginia chapter, Tech Times reported.[2] Microsoft had a letter of intent for up to 1.35 gigawatts at the Monarch campus, but exited the arrangement, after which Anthropic reportedly signed an agreement, confirmed by a regulatory disclosure from Aker ASA, a Nscale investor, Tech Times reported.[2]
Rivals CoreWeave and Nebius have seen shares drop amid borrowing concerns, according to CNBC.[1]