UK Power Networks told Nscale it could not supply enough power to the site until the early to mid-2030s, the Guardian reported.[1] Nscale, which is backed by tech companies including Nvidia, said it remains committed to the project and is exploring alternative power sources.[1] The end of the deal with Microsoft means Nscale has lost its only publicly announced customer for the Essex datacentre, and it is understood that UK Power Networks informed Nscale it would not be able to supply enough power to the Loughton datacentre until the early to mid-2030s.[1]